According to a published report, construction on the Brooklyn Bridge will force Manhattan-bound lanes to be closed during the weekend for six months next year. The New York Post says the overhaul of

News 12 Staff

Mar 1, 2009, 6:32 PM

Updated 5,773 days ago

Share:

According to a published report, construction on the Brooklyn Bridge will force Manhattan-bound lanes to be closed during the weekend for six months next year.
The New York Post says the overhaul of the bridge will take four years and cost between $200 million and $500 million.
The report notes that the state Department of Transportation deemed the bridge structurally sound in a 2006 study, but said some areas needed repairs.